WEST BAR BTR BLOCKS 1A & 1B, SHEFFIELD.

A glazed envelope with various cladding infill and firestopping works on Sheffield’s largest construction project in Sheffield over recent years.

Overview

Handshake Icon

Client

URBO

Cog Icon

Main Contractor

BOWMER & KIRKLAND

GBP Icon

Combined Value

£4.5M, MULTI-PHASE

Timelapse Icon

Duration

12 MONTHS

Shapes Icon

Sector

MIXED-USE, COMMERCIAL

List Icon

Status

COMPLETED

Flowchart Icon

Systems

SENIOR ALUMINIUM SYSTEMS PURE WINDOWS AND DOORS, HKL BALUSTRADE GUARDING, SENIOR ALUMINIUM SYSTEMS CURTAIN WALLING, ALUMINIUM COPINGS, ENTRANCE CANOPIES, IKON LOUVRE WALLING SYSTEMS, ASH & LACY CF3 ALUMINIUM INFILL PANELS WITH TENMAT FIRESTOPPING.

West Bar 2
West Bar 4

Contracted to design, supply, fabricate and install SAS windows, doors and curtain walling across two high rise buildings. HKL works varied to include cladding and accessories to various parts of the façade.

West Bar

SYSTEMS AND PRODUCTS.

Senior Aluminium Systems Pure Windows and Doors, HKL Balustrade Guarding, Senior Aluminium Systems Curtain Walling, Aluminium Copings, Entrance Canopies, Ikon Louvre Walling Systems and Ash & Lacy CF3 Aluminium Infill Panels with Tenmat Firestopping.

COMPLIANCE AND STANDARDS.

CWCT compliance test passed first time. BSA novated design review approved. £10m PI cover applied across both delivered phases. RIDDOR record on this project: zero in 22 months on site.
West Bar 2
West Bar 3
“Our site teams delivered 18 weeks of work in just 6 weeks.”

Ryan Damms, Operations Director,, HKL Specialists

“We were originally contracted to provide aluminium windows, doors and curtain walling. As our design engagement with Bowmer & Kirkland and 5Plus Architects progressed, our broad façade capability enabled us to take on additional scope and provide a more complete façade solution.

This allowed the project team to achieve the design intent for stacked windows incorporating aluminium slab-edge panels, while also developing a lightweight, bespoke Juliet balcony system. This solution overcame the challenge of being unable to install a traditional steel balcony to light-gauge SFS.

Bowmer & Kirkland also entrusted us to deliver further specialist elements, including:

• Louvre walling and doors
• Fire-rated doors
• Aluminium copings
• Entrance canopies

During the build programme, we were asked to accelerate our installation works to support the project’s critical path to watertightness. In response, our site teams delivered 18 weeks of work in just 6 weeks by working extended hours and weekends when required.

This project demonstrates our ability to deliver high-quality façades across multiple disciplines, while maintaining programme requirements and budget control. The commitment of our site teams played a key role in supporting the acceleration and helping drive the wider main contract programme forward.”

SELECTED WORK.

VIEW ALL WORK
6ML 33

6 MORE, LONDON

  • Commercial and Mixed-use
  • £3.2M
  • 9 MONTHS

Inherited 3 months after the targeted façade contractor appointment date. Despite this, HKL delivered to the original programme.

QEH East Block Coming soon

QUEEN ELIZABETH HOSPITAL (EAST BLOCK), BIRMINGHAM

  • 14 MONTHS

Rainscreen and curtain walling on a live, occupied NHS estate, with Schueco FW50+ and Trespa Meteon, BSA-aware delivery throughout.

Kirkstall Rd Coming soon

KIRKSTALL ROAD, LEEDS

  • Commercial and Mixed-use
  • £5M
  • 7 MONTHS

Pre-glazed window unit fabrication compressed the on-site programme. Currently windows complete and on-site completing retail curtain walling and doors