1500m2 of aluminium secret fix cladding completed at Lincoln University. 12 months later than originally planned due to Marcus Worthington’s administration but these things happen! Appointed by the Client and Caddick Construction to complete the works and achieve PC to the revised programme.
Great effort by our site team hanging in there on this one
Lincoln University Secret Fix